Environmental Review Process Proponent's Guide

Table of contents

1. Introduction

1.1 Purpose

This document is intended for use by proponents undertaking projects on First Nations reserve lands which are, pursuant to the Impact Assessment Act (IAA), subject to the Indigenous Services Canada (ISC) Environmental Review Process (ERP). It describes the steps associated with the ERP and the respective roles of proponents and ISC regional environment officers. It should be used before an application for a project on reserve lands is submitted to ISC. While this document provides general guidance on the ERP, proponents are encouraged to consult with ISC regional environment officers to discuss the appropriate application procedures and any additional requirements for their particular projects.

1.2 The environmental review process

ISC developed the ERP in 2013 to satisfy its obligations under the Canadian Environmental Assessment Act, 2012, and now under the Impact Assessment Act (IAA) and ensure that projects it supports on reserve lands proceed in an environmentally responsible manner. The IAA is federal environmental legislation that establishes a framework for evaluating the environmental impacts of designated projects and projects on federal lands. Under section 82 of the IAA, federal departments are required to ensure that proposed projects on reserve lands are not likely to result in significant adverse environmental effects before they take action or make a decision that would enable such projects to proceed. Most projects proposed on reserve lands are not designated projects and thus do not trigger a federal impact assessment, but they may be subject to a section 82 determination of environmental effects by the supporting federal department.

The ERP is a project planning tool that enables ISC to carefully consider the environmental effects of proposed projects and the impacts of those effects on Indigenous peoples and on health, social and economic conditions in communities. ISC must make such a determination of environmental effects before it can issue funding, land tenure or other authorizations (Appendix A) in support of projects on reserve lands.

The environmental review focuses on the proposed project components located on reserve lands and the full extent of the potential environmental effects associated with those components. Any environmental effects that originate on reserve lands but cross into an adjacent jurisdiction, such as a municipality, provincial lands or another reserve, must also be considered in the review. In some cases, the environmental effects of a project may trigger the Crown's legal duty to consult. For further information and guidance on fulfilling the duty to consult, see Appendix B).

Through the ERP, mitigation measures and best management practices that may eliminate or reduce the environmental effects of proposed projects can be identified, and follow-up programs may be recommended. The ERP helps ensure that proposed projects comply with all applicable federal and provincial laws, standards and permit requirements. Under the ERP, the level of environmental review is proportionate to the level and likelihood of potential environmental risk associated with execution of the proposed project. As a result, projects that are low in complexity and environmental risk, are routinely undertaken or have feasible, well-established mitigation measures do not require the same level of review as projects that have a greater potential to cause adverse environmental effects. Sections 2.2 and 2.3 of this document describe the process for assessing the risk of proposed projects and determining the appropriate level of review.

The ERP applies primarily to projects on reserve lands south of 60° north latitude and does not apply to projects in areas under land claim agreements as they are not considered to be federal lands as defined in the IAA.

1.3 Indigenous perspectives

The specific worldviews, customs, practices and traditions of Indigenous peoples are integral to the distinctive cultural identity of each First Nation and should be acknowledged and incorporated in every project development decision and throughout implementation and monitoring. ISC acknowledges the importance of Indigenous perspectives throughout the ERP and encourages proponents to engage meaningfully with concerned Indigenous communities, including different groups or subgroups of people within those communities.

2. Steps in the environmental review process

The ERP consists of 5 steps. A detailed description and walk-through of each step are provided below.

Figure 1. Steps in ISC's environmental review process
Figure 1 Steps in ISC's environmental review process
Text alternative for Figure 1. Steps in ISC's environmental review process

Step 1: Determine if the Environmental Review Process applies

Proponent completes and submits Sections 1 and 2 of the Project Description Form

  1. Is this a "designated project"?
    1. Yes: Refer to the Impact Assessment Agency of Canada.
    2. No: Proceed to question 2.
  2. Does the project involve a physical activity associated with a physical work on reserve?
    1. Yes: Proceed to question 3.
    2. No: The Environmental Review Process does not apply.
  3. Is the project in response to an emergency?
    1. Yes: The Environmental Review Process does not apply.
    2. No: Proceed to question 4.
  4. Will ISC issue funding or an authorization in relation to this project?
    1. Yes: Proceed to step 2.
    2. No: The Environmental Review Process does not apply.

Step 2: Identify level of environmental review

There is a minimum 30-day waiting period required between posting the Notice of Intent and posting the Notice of Determination on the Registry.

  1. Is the project excluded under the Ministerial Order?
    1. Yes: ISC completes a justification for project exclusion and may at a later date issue funding or authorizations in support of the project. Proceed to step 5, question 7.
    2. No: ISC will post a Notice of Intent with an invitation for public comments on the Registry. Proceed to question 6.
  2. Does ISC require additional information to perform a risk assessment?
    1. Yes: the proponent completes and submits Sections 3 to 5 of the Project Description Form. Proceed to step 3.
    2. No: A minor review will be conducted by ISC. No further review required. Proceed to step 3.

Step 3: Analysis of environmental effects

A risk assessment will be performed by ISC:

  1. Negligible risk: A minor review will be conducted by ISC. Proceed to step 4.
  2. Low risk: Simple environmental review must be completed by the proponent. Proceed to step 4.
  3. Medium risk: Detailed environmental review must be completed by the proponent. Proceed to step 4.

Step 4: Consideration of factors

ISC will consider factors outlined in section 84(1) of the IAA:

  1. Impacts on section 35 rights
  2. Indigenous knowledge
  3. Community knowledge
  4. Public comments
  5. Mitigation measures

Proceed to step 5.

Step 5: Decision and implementation

ISC posts a Notice of Determination on the Registry.

  1. Are significant adverse environmental effects likely?
    1. Yes: ISC cannot issue funding or authorization in support of the project, or ISC may refer the project to the Governor in Council to determine if effects are justified.
    2. No: ISC may issue funding or authorization in support of the project. The project may proceed.

2.1 Step 1: Determine if the ERP applies

In Step 1 of the ERP, the proponent must complete sections 1 and 2 of the Project Description Form in order for the project to be considered for the ERP.

Project Description Form

After it is determined that the ERP applies, the proponent will be required to complete the entire Project Description Form. This form provides the essential details of the proposed project and is used to assist ISC regional environment officers in

  • analyzing the project's potential environmental risks
  • making recommendations on mitigation as appropriate
  • determining the need for further environmental review

If it is determined that more information is required, the ISC regional environment officer will work with the proponent to acquire the necessary information. If you need additional support in completing the Project Description Form, please consult the Guide to Completing the Project Description Form.

Evaluation questions

After sections 1 and 2 of the Project Description Form are submitted, the proposed project is evaluated against 4 questions to determine if ISC is required to make a determination under section 82 of the IAA:

1. Is the proposed project a designated project?

Sections 82 and 83 of the IAA do not apply to designated projects identified in the Physical Activities Regulations or to projects designated by the Minister under section 9 of the IAA. Designated projects are projects with a large potential to result in significant adverse environmental effects within federal jurisdiction, and are therefore subject to a federal impact assessment undertaken by the Impact Assessment Agency of Canada (IAAC). Any designated project proposed, in whole or in part, on reserve land must be referred to the IAAC for consideration via the Impact Assessment Process.

Designated projects are not to be confused with the designated classes of projects set out in the Ministerial Order under section 88 of the IAA.

2. Does the project involve a physical activity associated with a physical work on reserve?

ISC is only required to make a determination under the IAA for projects which satisfy the definition of a project under section 81 of the Act, which states that projects include a physical activity in relation to a physical work on federal lands. All 3 of these elements must be satisfied in order for a proposed project to require a determination under the Act.

Definition of "project" under section 81 of the Impact Assessment Act

A project constitutes a physical activity involving a physical work on federal lands.

  • Physical activity: a physical activity includes carrying out tasks such as construction, modification, operation, and decommissioning
  • Physical work: a physical work includes structured built by human that have a defined area and fixed locality
  • Federal lands: federal lands are defined in section 2 of the IAA. They include First Nations reserves, national parks and military bases

A project, as defined in section 81 of the IAA, must meet all 3 conditions (physical activity, physical work and federal lands)

3. Is the project in response to an emergency?

Projects being carried out because of an emergency do not require a section 82 determination. This exemption applies in instances where the project is being carried out in response to matters of national security or to a national emergency as defined under section 3 of the Emergencies Act. This also applies when executing the project without delay will prevent damage to property or the environment or maintain public health or safety. ISC regional environment officers have the discretion to exempt a project from review because of emergency circumstances. ISC makes every effort to consider the environmental effects of such projects and apply mitigation measures to the extent possible in the circumstances.

4. Will ISC issue funding or an authorization in relation to the project?

A section 82 determination of environmental effects is only required when a federal authority has a decision to make that could enable a project to proceed on federal lands. As a result, ISC only conducts environmental reviews on projects proposed on reserve lands for which it provides funding or issues an authorization, for example, lease, permit or of which it is the proponent.

Due-diligence reviews

In some instances, proposed projects that do not meet 1 or more of the above conditions may still undergo a due-diligence environmental review. Typically, ISC will conduct due-diligence reviews when it is providing funding for activities that will be carried out off reserve, such as on pre-ATR (Additions to Reserve) or fee simple land. The due-diligence review process will be based on jurisdictional requirements, such as provincial or territorial approvals and project specifics. The decision to conduct a due-diligence review is at the discretion of the ISC regional environment officer.

The environmental review should also include a due-diligence consideration of legal requirements and industry standards, including the following:

  • legislative and regulatory requirements such as those under the Canadian Environmental Protection Act, 1999, the Species at Risk Act, the Migratory Birds Convention Act, 1994 and the Fisheries Act
  • applicable international codes, domestic standards and other stated norms for compliance

2.2 Step 2: Identify level of environmental review

In certain instances, a project that meets the definition and criteria of the classes of projects outlined in the Designated Classes of Projects Order may be exempted from environmental review and from publication on the Canadian Impact Assessment Registry (the registry). The ISC regional environment officer is responsible for making this decision based on information in sections 1 and 2 of the Project Description Form. Proponents may be required to provide additional information.

If it is determined that the ERP applies, the ISC regional environment officer is required to post a Notice of Intent on the registry. The public is encouraged to provide comments regarding that determination.

The legislative requirements for public participation are set out in sections 84 and 86 of the IAA. While ISC may always choose to do more, the IAA requires that ISC,

  • before making an environmental effects determination, post on the registry a notice that indicates that it intends to make a determination and that invites comments from the public, s. 86(1) for a period of at least 30 days, s. 86(2)
  • consider public comments when making the determination, s. 84(1)(d)
  • notify the public of the determination by posting a Notice of Determination on the registry that includes any mitigation measures taken into account in making the determination, s. 86(2). For more information about this requirement, see Step 5: Decision and implementation.

ISC will contact the proponent if more information is required to perform a risk assessment, which may include completing the Project Description Form, sections 3 to 5.

Once the Project Description Form is complete, ISC regional environment officers will review the information provided and perform a risk analysis to identify whether there is a need for further environmental review. The risk assessment will include the following considerations:

  • potential for pollution of soil, air, surface or groundwater
  • potential for effects on species at risk or migratory birds
  • potential for effects on fish or fish habitat
  • potential effects on other valued ecosystem components
  • potential effects on First Nations or treaty rights
  • potential for public concern
  • ability of any identified risks to be managed via best practices, standard mitigation measures, or regulatory means
  • potential effects on health, economic and social conditions, which includes human health, services and infrastructure, land and resource use, recreation, navigation, community well-being, structure, site, things of historical, archaeological, paleontological or architectural significance, and economic conditions and livelihoods

Using the results of this analysis, ISC regional environment officers will assign a level of review appropriate to the project, based on its potential risk to the environment. Below is a risk analysis table with examples of potential projects that fall under each category. Exceptions may apply.

Table 1. Level of environmental review and subsequent actions
Risk level Level of review Action required Project examples
Negligible Minor
  • No need for further environmental review after completion of sections 1 and 2 of the Project Description Form
  • Project effects can be managed through standard mitigation measures or best practices
  • Construction of a single house
  • Installation of telecommunications or Internet infrastructure
  • Maintenance activities
Low Simple
  • Entire Project Description Form may be completed
  • Mitigation measures must be identified for project components where potential environmental risk is identified
  • Any recommendations provided by the ISC regional environment officer, for example, best practices must be implemented
  • Construction of a water treatment plant
  • Construction of a residential subdivision
  • Construction of a gas station
Medium Detailed
  • Project is large or complex and risk and potential effects are not readily determined
  • Detailed assessment of potential environmental effects is required (for assistance, see the Guide to Completing a Detailed Environmental Review Report)
  • Construction of a stone quarry with a production capacity of less than 3.5 million tons per year
  • Construction of a waste incinerator
  • Construction of an all-season highway
High (potential for public concern) Referral for designation under s. 9(1) of the IAA
  • ISC may request that the Minister designate a physical activity that is not prescribed by regulations made under section109(b) of the IAA if, in its opinion, either the carrying out of that physical activity may cause adverse effects within federal jurisdiction or adverse direct or incidental effects, or public concerns related to those effects warrant the designation
  • If the Minister does not designate the project, it will undergo a detailed review
  • Projects that have a high environmental risk or a high level of public concern and are not already designated

Minor review

Many small-scale or routine projects supported by ISC are considered to have very low or negligible environmental risks because they have well-understood, predictable environmental effects that can be managed with standard best practices.

After the Project Description Form is reviewed and the review level for the proposed project is determined to be minor, the ISC regional environment officer will make a determination of environmental effects, which may include recommendations for best practices or mitigation, and the project may proceed.

The majority of projects that ISC reviews are considered minor projects.

Smaller projects will not require the same level of detail as larger, more complex projects.

Simple environmental review

Projects that have been assigned a "low" risk level will require further environmental review. Sections 3 to 5 of the Project Description Form specify the additional information required for such projects. For any interaction between project activities and environmental components where potential risk is identified, the proponent must propose appropriate mitigation measures to reduce or remove that risk.

Detailed environmental review

When a proposed project is large or complex in nature, the interactions between the project and the environment are less predictable, and identifying the potential adverse effects and appropriate mitigation measures will require careful analysis. For these medium-risk projects, ISC will require a Detailed Environmental Review Report before it can make its determination. Proponents are referred to the Guide to Completing a Detailed Environmental Review Report, which sets out the requirements for preparing a Detailed Environmental Review Report. Although the specific information may vary from project to project, the report should include the following:

  • brief description of the proposed project and project area
  • summary of the project activities that have the potential to affect the environment
  • summary of the anticipated environmental effects
  • summary of the proposed mitigation measures to address the environmental effects
  • summary of any residual effects
  • summary of any follow-up programs proposed, if applicable
  • analysis of the significance of any residual effects after mitigation is applied
  • identification of any cumulative effects
  • analysis of climate change adaptation and sustainability considerations for specific project components

The Detailed Environmental Review Report should be prepared by a qualified independent third partyFootnote 1 and submitted to an ISC regional environment officer for review and determination of the environmental effects.

2.3 Step 3: Analysis of environmental effects

In section 81 of the IAA, environmental effects are defined as "changes to the environment and the impact of these changes on the Indigenous peoples of Canada and on health, social or economic conditions."

For each adverse effect identified in the Project Description Form, mitigation measures should be proposed with the aim of eliminating, reducing or otherwise controlling the adverse effect. Mitigation may take many forms, including revising the project design, adding some feature or changing the location or timing of project work. For a list of common mitigation measures, see Appendix C.

Effects predicted to remain after mitigation measures have been applied are also evaluated for their significance. In determining the significance of adverse environmental effects, ISC may consider:

  • whether the project's outcomes are likely to exceed thresholds established under any regional study
  • whether the timing of the proposal could result in significant interactions with the environment (for example construction or operation of a project during migratory birds' nesting season)
  • whether the environmental effects and mitigation measures of similar projects could be applied to the current project
  • the level of public concern
  • the potential for cumulative effects
  • criteria such as the scale, magnitude, duration, reversibility and ecological context (in other words how the region has already been affected by human activity) of potential effects.

When determining the likelihood of significant adverse effects, the probability that the effects will occur and the level of scientific uncertainty associated with the information and methods used in the environmental review must be considered. For a more comprehensive discussion on how significance and likelihood are determined, see Determining Whether a Project is Likely to Cause Significant Adverse Environmental Effects.

During the review, ISC may need to seek (or require the proponent to seek) the input of other federal departments or agencies, such as the Department of Fisheries and Oceans or Environment and Climate Change Canada, regarding potential effects, mitigation, best practices, and applicable regulatory authorizations. While the IAA does not set out specific timelines for such input, departments and agencies are encouraged to work cooperatively and respond to requests for information and expertise in a timely manner.

Climate change adaptation and sustainability

The Government of Canada has made a strong commitment to reduce environmental pollution and adapt to climate change, including through close collaboration with Indigenous groups. ISC encourages project proponents to take long-term sustainability and climate resiliency into account when initiating and developing projects.

Consider the following:

  • the interconnectedness and interdependence of human-ecological systems
  • the well-being of present and future generations
  • maximizing the project's overall benefits and minimizing its adverse effects
  • the precautionary principle (uncertainty and the risk of irreversible harm)

For most minor and simple reviews, the projects do not considerably add to the issue of environmental pollution, however a climate change lens should be applied to all levels of review and is at the discretion of the regions. Proponents should always keep low-carbon alternatives, adaptability and sustainability in mind when developing and initiating a project.

For medium- and high-risk projects, climate change considerations must be considered in the Detailed Environmental Review Report. For information on what components to address concerning climate change, see the Guide to Completing a Detailed Environmental Review Report.

2.4 Step 4: Consideration of factors

ISC's determination regarding whether the project is likely to cause significant adverse environmental effects must be based on the following factors specified in section 84(1) of the IAA:

  1. Indigenous rights
  2. Indigenous knowledge
  3. Community knowledge
  4. Public comments
  5. Mitigation measures

ISC regional environment officers use the information provided in the Project Description Form or Detailed Environmental Review Report when considering these factors in their analysis. Should further information be required, the ISC regional environment officer will reach out to the proponent directly.

1. Indigenous rights

ISC will consider any adverse impact that the project may have on the ability of Indigenous peoples of Canada to exercise their treaty rights, as recognized and affirmed in section 35 of the Constitution Act, 1982. In particular, the ISC regional environment officer will take a holistic approach in analyzing potential impacts on treaty rights, including the use of qualitative and quantitative measures and considerations informed by Indigenous knowledge, where appropriate.

2. Indigenous knowledge

Indigenous knowledge is holistic and can provide invaluable insights on the following:

  • project design
  • the environment, social, cultural, economic and health conditions, Indigenous governance and resource use
  • identification of valued components, indicators or measurement methods
  • identification and assessment of changes to the environment
  • identification of mitigation measures, not only in relation to impacts on Indigenous peoples but more broadly
  • identification of impacts on treaty rights
  • considerations for follow-up and monitoring

ISC regional environment officers will consider Indigenous knowledge with respect to the proposed project in determining the likelihood that it will cause adverse environmental impacts.

3. Community knowledge provided with respect to the project

Community knowledge refers to information held by community members or resource users, like farmers, hunters, fishers and naturalists, who are familiar with the environment in a specific geographic area. Community knowledge is often developed through long-term association and interaction with the environment or a resource. It may be useful in the evaluation of environmental effects and the development of mitigation measures.

For example, anglers in a specific area may know where the best fishing spots are and may therefore be able to help identify potential fish habitats. Similarly, local naturalists' observations may help identify wildlife species that frequent the project area.

Where applicable, ISC regional environment officers will analyze community knowledge when making their determination.

4. Comments received from the public and posted on the Canadian Impact Assessment Registry

Before making a determination, ISC, as the federal authority, must post a notice of intent on the Canadian Impact Assessment Registry indicating the intention to make a determination and inviting input from the public. The comment period is 30 days. In making a determination, the ISC regional environment officer must demonstrate that all comments received through the registry have been taken into consideration in the decision-making process.

5. Mitigation measures

Where there is a possibility that a proposed project will cause adverse environmental impacts, mitigation measures may be proposed. If the proponent does not propose mitigation measures in the Project Description Form or the Detailed Environmental Review Report, the ISC regional environment officer may propose mitigation measures as a condition of approving the project. When determining mitigation measures, the ISC regional environment officer will consider whether or not the proposed measures are technically feasible and economically feasible for the proponent.

Technically feasible means that the action can be successfully implemented under the specific circumstances of the project and either is generally accepted, common, well-documented or tested or, if relatively new, has a high estimated probability of successful implementation. The following are examples of criteria that may be used to determine technical feasibility:

  • availability of energy sources
  • ability to implement in local climate
  • requirement for supporting infrastructure
  • inherent risks
  • use of proven technology
  • distance to main project site

Economically feasible means that the costs associated with the action are not prohibitively high. In reviewing a proponent's views regarding the extent to which mitigation measures are economically feasible, the ISC regional environment officer should consider various economic criteria in the context of the particular project. The following are examples of such economic criteria:

  • estimated costs (capital and operating)
  • revenue
  • profit
  • production forecasts

Before making a final determination, ISC must be satisfied that the proposed mitigation measures will be implemented for the proposed project. Mitigation measures are often linked to any authorization or funding agreement issued by the department. The proponent will be required to implement the proposed mitigation measures under the terms of the authorization or agreement.

Monitoring and follow-up programs

The determination of environmental effects may include a requirement for post-project compliance reporting and/or follow-up/monitoring programs.

A monitoring program, with clearly defined roles and responsibilities, may be implemented. This ensures that the proposed mitigation strategies or follow up programs identified in the environmental review will be implemented. Monitoring programs can be linked to all phases of development, from pre-construction, construction and operation to decommissioning and abandonment. The proponent may be asked to submit periodic reporting for each phase of the project.

If a project is located in an environmentally sensitive area, has generated substantial public concern, has mitigation measures that are atypical or not well-established, or has poorly understood potential effects because of its novelty or new technology, a follow-up program may also be undertaken. This will help detect unanticipated environmental effects and support or verify predictions that "no significant environmental effects" are likely.

2.5 Step 5: Decision and implementation

The ERP concludes when ISC issues a determination regarding the likelihood of significant adverse environmental effects, as required by the IAA (s. 82).

If the environmental review determines that carrying out a project is likely to cause significant adverse environmental effects, ISC cannot provide support (such as, funding or regulatory authorization) to the project. It may, in consultation with the proponent, seek a Governor in Council decision on whether the significant adverse environmental effects are justified in the circumstances s. 82(b) of the IAA. If the Governor in Council determines that the significant adverse environmental effects are indeed justified, ISC would then be able provide support to the project.

If the environmental review concludes that the project is unlikely to cause significant adverse effects, ISC may proceed with its funding and regulatory authorization, such as a permit or lease, in support of the project, as long as all other applicable program requirements are met. As a condition of funding or regulatory approval, ISC will issue terms and conditions or delivery requirements to ensure the proponent will meet IAA requirements, including mitigation measures, during project implementation (Appendix C).

Compliance and reporting

At project close, the proponent may be asked to submit a Mitigation Measures Compliance report as part of the end-of-project reporting requirements. This report is used to confirm that the mitigation measures prescribed in the environmental review were incorporated into project design and tender documents and implemented accordingly over the course of the project.

This report must be completed for projects that underwent a Detailed Environmental Review. At ISC's discretion, it may also be required for projects that underwent a Simple Environmental Review. It is generally not required for projects that underwent a minor review.

If a Mitigation Measures Compliance report is deemed necessary, the requirement will be included in the funding terms and conditions or the delivery requirements. Whenever there are terms and conditions or mitigation measures associated with a project's approval, ISC will require documentation showing that the conditions were met before it certifies the project as "completed." Any mitigation measures, monitoring, or enforcement requirements (including periodic environmental audits, if applicable) identified in an environmental review must be incorporated into the terms and conditions of the regulatory authorization issued by the department.

Timelines

ISC aims to complete reviews in a timely fashion so that projects are not delayed unnecessarily and mitigation measures can be built into the project design. The ERP should be initiated as early as possible in the planning stages of any proposed undertaking, to ensure that the environment is appropriately considered and any adverse effects are mitigated.

For projects that will require posting on the Registry, the proponent must take into account the 30-day public comment period associated with IAA requirements.

3. Roles and responsibilities

The roles and responsibilities of ISC and the project proponent through the 5 steps of the ERP are outlined below.

Step 1. Determine if the Environmental Review Process applies
Role Responsibility
1. Submit sections 1 and 2 of the Project Description Form to ISC. Proponent
2. Determine if the proposed undertaking is subject to the Environmental Review Process, and advise the proponent accordingly. ISC regional environment officer
Step 2. Identify level of environmental review
Role Responsibility
1. Post a Notice of Intent on the registry with an invitation for public comment. ISC regional environment officer
2. At ISC's request, submit a complete Project Description Form. This information should be provided by someone with knowledge of the site and the project's potential effects. Proponent
3. Review the Project Description Form. If the project requires further review, ask the proponent to complete sections 3 to 5 of the Project Description Form. ISC regional environment officer
4. Perform an environmental risk assessment with all the information provided about the project. ISC regional environment officer
5. As requested, identify any additional information beyond that required in the Project Description Form that may be relevant to the environmental review. Proponent
Step 3. Analysis of environmental effects
Role Responsibility
1. If applicable, identify the potential environmental effects along with appropriate mitigation measures and their implementation and discuss the residual effects and their significance. Proponent
2. Have the Detailed Environmental Review, if required, completed by a qualified independent environmental professional who is familiar with the project, its location and federal or provincial environmental assessment legislation. Proponent
3. Ensure that the First Nation has been properly and fully informed and engaged. Proponent
4. Ensure that the legal duty to consult is met, when applicable. ISC regional environment officer
5. Request additional information or revisions as required. Discuss the project with the proponent and any stakeholders, and take any concerns into account in decision-making. ISC regional environment officer
6. Revise sections 3 to 5 of the Project Description Form or the Detailed Environmental Review Report as requested by ISC or other federal authorities involved in the review. Ensure that the project design reflects all mitigation measures and best practices identified in the environmental review. Proponent
Step 4. Consideration of factors
Role Responsibility
Consider the factors specified in section 84(1) of the IAA. ISC regional environment officer
Step 5. Decision and implementation
Role Responsibility
1. Taking into consideration the environmental review and any concerns raised by other stakeholders, make a determination on the significance of the adverse environment effects, if any. ISC regional environment officer
2. For projects deemed unlikely to cause significant adverse environmental effects, approve funding or departmental authorizations in support of the project, provided all other applicable program requirements are met. Post a Notice of Determination for the project on the Registry. ISC regional environment officer
3. Obtain all required permits and licences. A band council resolution will be required to initiate the issuance of ISC authorizations such as an Indian Act permit or lease. Proponent
4. During project execution, ensure all mitigation and best management practices identified during the environmental review are implemented. Proponent
5. Advise ISC of any changes to the project scope or environmental conditions in the project area. Bear in mind that the project received its environmental approval as described. If there are any substantial changes after approval, the project's effects may need to be reassessed. Proponent
6. For projects deemed likely to cause significant environmental effects, ISC may request that the Governor in Council determine whether the effects are justified in the circumstances, pursuant to section 90 of the IAA. If the Governor in Council decides that the effects are justified, they must be mitigated to the extent possible. ISC regional environment officer in consultation with the proponent
After the environmental review
Role Responsibility
Submit the Mitigation Measures Compliance report as part of project completion reporting, if required by ISC. Proponent

4. Important notes

4.1 Submitting a Project Description Form

The ERP should commence early in the planning stages of the project, once the details of the project are known. That being said, the timing and process for submitting a Project Description Form to meet a program's application requirements will vary with the specific ISC program and region. Proponents are strongly encouraged to contact program officers or advisors in the early stages of project planning and obtain program-specific advice on how the ERP fits into the program's review and approval process.

4.2 Environmental review costs

In ISC programs that fund design or business development costs, the environmental review may be considered part of those overall development and design costs. For projects where ISC's only involvement is to provide Indian Act land tenure or Dominion Water Power Act authorizations, the proponent of the project is responsible for funding the environmental review.

4.3 Feasibility study, capital planning study, waste management plan, and business plan

A study funded by ISC that is not a physical activity in relation to a physical work is not considered a project as defined in the IAA, so the ERP does not apply (see the definition of a project). Nevertheless, the ISC Regional Environment Officer should be contacted for advice on any study or plan relating to a planned project on federal lands. Early identification of regulatory requirements or potential environmental issues at the planning stage may save time or costs later on.

4.4 ERP for projects sited both on and off reserve

Section 82 requirements only apply on federal lands, so only the on-reserve portion of the project would be subject to the ERP. Take the example of the proposed construction of a winter road joining 2 or more communities. The on-reserve portion(s) would be subject to the ERP in accordance with section 82 of the IAA. For the off-reserve portion, the review process required will be based on jurisdictional requirements such as provincial and territorial environmental assessment approvals and permits, project specifics and regional requirements. In these cases, ISC may consider using the provincial process to meet its requirements for a determination of environmental effects, in keeping with the 1 project, 1 review principle. Regardless, the proponent must demonstrate that it has met all applicable requirements before it receives ISC funding approval.

4.5 When another federal department is funding an on-reserve project

For some projects on federal lands or outside Canada, more than one authority may have responsibilities under sections 82 and 83.

The Federal Coordination Regulations made under the Canadian Environmental Assessment Act of 1992, which required authorities to work together to ensure a coordinated approach to decision-making, are no longer in force. However, where multiple authorities are required to make a determination of significance on the same project, they are encouraged to work together in completing their analysis or producing a single report. It is up to each group of authorities working together to determine the approach they will take and how they would likely collaborate in their consultation approach. This best practice ensures that the public is provided with a single window to the assessment of a given project, regardless of how many authorities are required to make determinations.

While authorities are encouraged to work together in such cases, each authority must ensure that it meet its obligations under sections 81 to 91 of the IAA. This means that, even when working with others, each authority must meet the following requirements:

  • Posting public notices (for example, the Notice of Intent and the Notice of Determination) on the Registry and ensuring that the minimum 30-day period between the notices is met
  • Completing a determination of adverse environmental effects, based on a consideration of all factors set out in section 84

4.6 Projects on lands managed by First Nations under the First Nations Land Management Act and the ERP

Under the Framework Agreement on First Nation Land Management and the First Nations Land Management Act (FNLMA), the responsibility for authorizing leases, permits, or other land instruments in support of a project is transferred to the First Nation, and hence the First Nation has jurisdiction over environmental assessments on its land. Where a First Nation operates under the FNLMA with its own environmental assessment process and an ISC authorization is required, ISC will work with the First Nation to minimize duplication and follow the "1 project, 1 review" principle.

If the First Nation and the federal authority agree on a harmonized approach to the project's assessment, the federal authority will post the Notice of Intent on the registry. The federal authority will also follow the First Nation's processes for receiving comments from the community. The results of the environmental assessment should be shared between the First Nation and the federal authority to ensure that both parties have sufficient evidence to make their independent determinations. Once the federal authority makes its determination, it will post the Notice of Determination on the registry.

If an agreement cannot be reached on a way to harmonize the First Nation's process with the federal authority's requirements for an environmental assessment, the federal authority may have to conduct an environmental assessment separate from the First Nation's assessment, which will mean 2 assessment for the project. However, the federal authority will still have to work with the First Nations to address section 84 considerations such as Indigenous and community knowledge.

The parties should work together to resolve any disagreement in findings, however, the decision made by the First Nations on whether or not the project will move forward, must be respected.

Proponents should contact the appropriate First Nations for information about its environmental assessment requirements.

4.7 When seeking funding or statutory approval for a project that is already wholly or partially constructed

Occasionally, projects are initiated before or during the ERP. The fact that physical work has already begun on a project does not alter ISC's obligation to ensure that an environmental review is completed, and a determination of environmental effects made, before it provides statutory authorizations or financial assistance.

Proponents should consider the following risks before undertaking a project for which an environmental review has not been completed:

  • delay in funding release until environmental issues are properly addressed
  • additional costs to rework the project design
  • potential for environmental damage
  • potential violations of the Canadian Environmental Protection Act, the Species at Risk Act, the Fisheries Act or other legislation

5. Disclaimer and updates

This document outlines the environmental review requirements for proposed projects on First Nations reserve land. The referenced regulations are considered current at the time of publication. Although every effort has been made to address and include all applicable regulations and guidelines, this document is not considered exhaustive. The project proponent is responsible for addressing all aspects of the proposed project, including any additional aspects not mentioned here.

This guide will be updated periodically. Users are responsible for ensuring that they use the latest version in their work. The title page indicates when the guide was last updated. Should this guide be updated during the planning or execution of an applicant's project, the previous version of the document remains applicable for that project.

All documents generated as part of the ERP – including the Project Description Form, environmental review reports and any associated annexes and appendices – are subject to be released to interested parties under access-to-information and privacy legislation. They may also be circulated to relevant government departments and agencies. A project summary may be posted on the ISC website and on the Canadian Impact Assessment Registry. Accordingly, before any potentially confidential project information is submitted, it should be discussed with ISC.

The Government of Canada accepts no liability whatsoever for any claim that might in any way arise as a consequence of the Government of Canada's handling, use, publication or release of project information, either in whole or in part. Proponents are wholly responsible for ensuring that their project information is substantially accurate and that nothing contained in it is subject to any confidentiality requirements. Proponents must not submit confidential, personal or proprietary information that is not to be made public.

Appendices

Appendix A: Reasons for an ISC environmental review

The list of reasons below should not be considered exhaustive, and the proponent should confirm with ISC whether the department considers that the ERP has been started for a specific project.

List of ISC reasons for a determination under section 82 of the IAA:

  1. ISC is the project proponent
  2. ISC is providing financial assistance to the project:
    • Funding from ISC programs (community infrastructure, housing, economic development), with the exception of block funding
  3. ISC is issuing a statutory authorization in support of the project:
    • Ministerial expenditure decisions to release band moneys (Indian Act, ss. 64, 66 and 69)
    • Authorization for use of First Nations lands for the purpose of Indian schools, administration of Indian affairs, Indian burial grounds or Indian health projects (Indian Act, s. 18(2))
    • Issuance of a Certificate of Possession for the purpose of enabling a First Nation member to construct a dwelling or other building (Indian Act, s. 20)
    • Issuance of a permit for occupation or use of First Nations land (Indian Act, s. 28(2))
    • Sale or lease of surrendered or designated lands (Indian Act, s. 53(1))
    • Lease to a third party of land allotted to a band member (Indian Act, s. 58(3))
    • Disposal of sand, gravel, clay or other non-metallic substances or the taking of these materials, on or under First Nations lands (Indian Act, s. 58(4)(b))
    • Issuance of a permit or lease for the exploration or development of minerals (Indian Mining Regulations, ss. 5(2), 6(1))
    • Issuance of a permit to operate a garbage dump, dispose of or store waste, or burn waste on First Nations lands (Indian Reserve Waste Disposal Regulations, s. 5)
    • Issuance of a permit to First Nations members to cut timber for sale, Indian Timber Regulations, s. 5(1)
    • Issuance of a licence for cutting and removing timber from First Nations lands (Indian Timber Regulations, s. 9) or varying the terms of a timber licence (s. 22(1))
    • Issuance of surface leases and rights-of-way (Indian Oil and Gas Regulations, s. 73(3)) or exploratory work on First Nations lands that requires an exploratory licence (Indian Oil and Gas Regulations, s. 29(1))
    • Oil and gas exploration on First Nations lands that requires a right of entry (Indian Oil and Gas Regulations, s. 30)
    • Issuance of a lease to commence production of crude bitumen (Indian Oil and Gas Regulations, 1995, s. 39(1))
    • Amendment of a lease or permit to provide for production of crude bitumen (Indian Oil and Gas Regulations, 1995, s. 39(3))
    • Taking of lands by local authorities (Indian Act, s. 35(1))
    • Acceptance of an absolute surrender or designation (Indian Act, s. 39(1)(c))
    • Authorization from the Minister to enter on, use, occupy, take and acquire any lands that may be required for a hydroelectric project. (Dominion Water Power Act, s. 7(1))
    • Authorization from the Governor in Council necessary to bring about the joint development and operation of a hydroelectric project, where such is economically desirable (Dominion Water Power Act, s. 9)
    • Licences, authorizations and approvals under sections 8(1), 12(2), 21, 25(2), 40(1), 46, 49(3), 50 or 69(3) of the Dominion Water Power Regulations
    • Issuance of a Ministerial Loan Guarantee (Indian Act (s. 89(1)), which protects First Nations property from seizure by a non-Indian (for example, lender)

Appendix B: Regulatory agencies, legislation, and guidelines

The following table lists regulatory agencies, legislation and guidelines that may be involved in a project on First Nations reserve land. The list is a working aid and is not exhaustive. The proponent is responsible for ensuring that the project incorporates the most current references and complies with all legislative requirements.

Regulatory reference material and guidance

Federal legislation
Provincial and territorial legislation
Consultation
Traditional ecological knowledge
Consultation
Technical documents
Archaeological, cultural and heritage resources
Climate change
Cumulative effects
Disposal at sea
Emergency preparedness
Environmental assessment and review
Environmental management strategies
Environmental monitoring
Fish and fish habitat
Remediation and reclamation
Species at risk and survey methodologies
Storage
Waste
Water quality (ground and surface water)
Wetlands
ISC Programs
Lands
Indian moneys
Community infrastructure
Ministerial loan guarantees

Appendix C: Mitigation measures

Table C1. Types of mitigation measures with examples
Type of mitigation Description Examples
Compensate Mitigation measures that compensate for the environmental effect through other means.
  • Replace wetland habitat that will be lost
  • Award financial compensation for lost resources or other opportunities
Repair Mitigation measures that repair the situation after an environmental effect has occurred.
  • Rehabilitate site area by re-vegetating and landscaping
  • Spill containment and clean-up
Reduce Mitigation measures that reduce the magnitude or duration of the effect.
  • Establish berms, breaks or ditches to limit soil run-off during construction
  • Ensure all equipment is properly tuned and fitted with standard emissions control devices
Avoid Mitigation measures that avoid the effect all together.
  • Avoid work during critical nesting periods
  • Do in-water work outside spawning periods

Appendix D: Glossary

Unless otherwise noted, all definitions are taken verbatim or in modified form from the Impact Assessment Act.

Agency
Impact Assessment Agency of Canada
Aquatic species
Wildlife species that are fish, which includes all or any parts of fish, shellfish, crustaceans, marine animals or the eggs, sperm, spawn, larvae, spat and juvenile states of fish, shellfish, crustaceans and marine animals; or a marine plant, which includes all benthic and detached algae, marine flowering plants, brown algae, red algae, green algae and phytoplankton (Fisheries Act)
Band-owned fee-simple land
Off-reserve land which is owned by the band for the purposes of economic development funding
Baseline studies
Work done to collect, analyze and interpret information on the status or trends of the environment likely to be affected by a development action, prior to the beginning of the project. A benchmark for measuring changes caused by the project
Canadian Environmental Protection Act (CEPA)
An Act respecting pollution prevention and the protection of the environment and human health in order to contribute to sustainable development
Cumulative effects
A change in the environment caused by multiple interactions among human activities (for example, projects) and natural processes that accumulate across space and time
Decommissioning
The restoration work required to minimize the ongoing adverse environmental effects associated with a project, or component of a project, that is no longer required
Designated project
Categories of projects with a large potential to result in significant adverse environmental effects within federal jurisdiction (described in the Physical Activities Regulations)
Designated projects are physical activities that They include any physical activity that is incidental to those physical activities but not a physical activity designated by regulations made under paragraph 112(1)(a.2).
Ecosystem
A community of interdependent plants and animals together with the environment which they inhabit and with which they interact
Environment
The components of the earth, including:
  • land, water and air, including all layers of the atmosphere
  • all organic and inorganic matter and living organisms
  • the interacting natural systems that include components referred to in first 2 paragraphs
Environmental review
An analysis of the environmental effects of any ISC-supported project proposed on federal lands, conducted in accordance with section 82 of the Impact Assessment Act
Environmental effects
Unless the context requires otherwise, changes to the environment or to health, social or economic conditions and the positive and negative consequences of these changes
Federal authority
Federal lands
  • Lands that belong to Her Majesty in right of Canada, or that Her Majesty in right of Canada has the power to dispose of, and all waters on and airspace above those lands, other than lands under the administration and control of the Commissioner of Yukon, the Northwest Territories or Nunavut
  • The following lands and areas:
    • the internal waters of Canada, in any area of the sea not within a province
    • the territorial sea of Canada, in any area of the sea not within a province
    • the exclusive economic zone of Canada
    • the continental shelf of Canada
  • Reserves, surrendered lands and any other lands that are set apart for the use and benefit of a band and that are subject to the Indian Act, and all waters on and airspace above those reserves or lands
Follow-up program
A program for
  • verifying the accuracy of the environmental assessment of a designated project
  • determining the effectiveness of any mitigation measures
Habitat
All the elements of earth that are used by wildlife species to sustain themselves throughout their life cycles. This includes the spaces (for example, terrestrial and aquatic) that they require as well as the properties of those spaces (for example, biota, climate, soils, ecological processes and relationships). Habitats function in providing such needs as food, shelter and a home place. Habitats can be thought of as distinctive places or ecosystems, such as prairie habitats or Arctic habitats, Environmental assessment best practice guide for wildlife at risk in Canada (Environment Canada).
Impact Assessment Act:
An Act respecting a federal process for impact assessments and the prevention of significant adverse environmental effects replaces the Canadian Environmental Assessment Act, 2012.
Impact assessment (IA)
An assessment of the effects of a designated project that is conducted in accordance with the Impact Assessment Act. IA is a process for identifying project-environment interactions, predicting environmental effects, identifying mitigation measures, evaluating significance, reporting and following up to verify accuracy and effectiveness. IA is a planning tool to help guide decision-making and project design and implementation.
Mitigation measures
Measures to eliminate, reduce, control or offset the adverse effects of a project or designated project, including restitution for any damage caused by those effects through replacement, restoration, compensation or any other means.
Monitoring
Systematic observation and/or collection of data and evaluation of environmental/socio-economic parameters or processes.
Physical activity
Any proposed construction, operation, modification, decommissioning, abandonment, or other undertaking in relation to a physical work.
Physical work
A structure built by humans that has a defined area and fixed locality (for example, it has a permanent location).
Project
A physical activity that is carried out on federal lands or outside Canada in relation to a physical work and is not a designated project, sometimes informally referred to as a non- designated project.
Proponent
The person or entity that proposes the carrying out of a non-designated project or a designated project.
Remediation
Removal, treatment, destruction or containment of soils, sediments, wastes, groundwater or surface waters contaminated by hazardous substances.
Residual effects
Predicted adverse environment effects that remain after mitigation measures have been applied.
Species
Any indigenous species, subspecies, variety or geographically or genetically distinct population of wild fauna or flora, Environmental assessment best practice guide for wildlife at risk in Canada.
Reserve
  • A tract of land, the legal title to which is vested in Her Majesty, that has been set apart by Her Majesty for the use and benefit of a band
  • Except in subsection 18(2), sections 20 to 25, 28, 37, 38, 42, 44, 46, 48 to 51 and 58 to 60 and the regulations made under any of those provisions, includes designated lands, Indian Act
Valued ecosystem component
The environmental element of an ecosystem that is identified as having scientific, social, cultural, economic, historical, archaeological or aesthetic importance. The value of an ecosystem component may be determined on the basis of cultural ideals or scientific concern. Valued ecosystem components that have the potential to interact with project components should be included in the assessment of environmental effects.

Did you find what you were looking for?

What was wrong?

You will not receive a reply. Don't include personal information (telephone, email, SIN, financial, medical, or work details).
Maximum 300 characters

Thank you for your feedback

Date modified: